Project
Vinifera environmental water delivery.
Location
Situated 5KM from Vinifera in the Nyah Vinifera Forrest is a large wetland capable of holding up to 1100ML.
Requirements
To deliver 1100 ML of environmental water from the Murray River to Vinifera Wetland.
Services Provided
Services Provided here
Equipment Used
- 1 : 12 inch centrifugal pump
- 1 : 45 degree elbow
- 1: 1000 liter bulk fuel tank fully double bunded
- 22 meters of 12 inch suction line with filter
- 1 Siemens water meter
- 120 meters of 12 inch delivery line
- 1: 12 inch flute to minimize soil erosion and environÂmental impact
- 1: 6 meter x 6 meter square of geofabric to minimize soil erosion and environmental impact
- 1 Adcon telemetry unit giving real time monitoring with data logging back to a hosted website
- Services provided: site inspection with Mallee CMA staff discussing any cultural heritage issues and any other enÂvironmental considerations
- Coordination of traffic management plan
- Coordination of earthworks
- Designing a safety management plan
- Monitoring of wetlands
- Refueling, service and maintenance of pumps