Project
Wallpolla East environmental water delivery.
Location
Wallpolla Island.
Requirements
To deliver 1OOOML of environmental water from the Murray River to Wallpolla East Wetland.
Services Provided
- Designing of a detailed system to specific site conditions.
- Site inspection with Mallee CMA staff discussing any culĀtural heritage issues and any other environmental considĀerations.
- Coordination of traffic management plan.
- Coordination of construction of earthworks.
- Designing a safety management plan.
- Monitoring of wetlands.
- Refueling, servicing and maintenance of pumps.
- Regulation of flows to suit timelines.
Equipment Used
- 1 : 12 inch pump.
- 1 : 600 liter diesel tank fully bunded.
- 1 Siemmens water meter.
- 27 meters of 12 inch suction line.
- 1 suction manifold and pipes.
- 150 meters of 12 inch delivery line.
- 1: 12 inch flute to minimize soil erosion and environmental impact.
- 1 : 6 meter x 6 meter geofabric to minimize soil erosion and environmental impact.
- 1 Adcon telemetry unit giving real-time monitoring with data logging back to a hosted website.