Murray Bridge -
Flood Emergency.

We undertake works big and small, anywhere in Australia, no matter the challenge.

In March 2023 Millewa Pumping were employed for nine months to dewater the inundated dairy farms from flood waters. This required a prompt and efficient response, and the project required a number of pumps ranging from six inch in diameter to 26 inch in diameter to remove the flood waters.

Murray Bridge - SA

Equipment used at Murray Bridge site:

4 x 26-inch pumps and appropriate pipework

3 x 6-inch pumps and appropriate pipework

2 x 8-inch pumps and appropriate pipe work

11 x 12-inch pumps and appropriate pipework

3 x 20-inch pumps and appropriate pipework

2 x 10000 litres fuel storage tank

1 x 5000 litres fuel storage tank

1 x 1800 litres fuel storage tank

3 x 1000 litres fuel storage tank


Project Outcomes:
The objective of this project is to effectively manage floodwater entering the dairy farming properties through dewatering systems. By implementing efficient dewatering methods, the project aims to minimise the impact on dairy operations, safeguarding infrastructure and the surrounding environment and community.